Customer area · Pricing

Tariffs and scales of tariffs of Lomé Container Terminal

Check the published amounts for ground handling, the Gate and Yard services, equipment rental, and container parking.

Money

XOF and EUR

Handling

20 and 40 feet

Date of effect

Not indicated

VAT

18%

Before any operation

What the published grid specifies

This official grid indicates the rates and scales for land handling operations for 20- and 40-foot containers, as well as the equipment rental amounts.
To be checked before billing. Confirm the tariff, the billing unit and the VAT treatment with LCT. The 45-foot handling charges are not included, as the documents submitted contain a contradictory value for the hinterland import with truck loading.

Gate and Yard Services

Land handling

The tables reproduce the amounts in XOF and EUR published by LCT for the 20-foot and 40-foot containers.

Land handling at the import

Performance
20 feet
40 feet
XOF
EUR
XOF
EUR
Import hinterland, loading on truck
99 929
152,34
167 426
255,24
Import hinterland, LCT unloading
124 992
190,55
217 553
331,66
Importing from a coastal transit country, loading on a truck
121 250
184,84
201 960
307,89
Importing coastal transit countries, LCT discharge
146 314
223,05
252 087
384,30
Local import, loading on truck
125 524
191,36
209 468
319,33
Local import, LCT depuration
175 651
267,78
284 658
433,96
Free trade zone import, loading on truck
125 524
191,36
209 468
319,33
Free trade zone, LCT warehousing
175 651
267,78
284 658
433,96

Land handling for export

Performance
20 feet
40 feet
XOF
EUR
XOF
EUR
Export hinterland, linked to the port
108 593

165,55

181 289

276,37

Export hinterland, subcontracting in the city

58 466

89,13

106 098

161,75

Coastal exporting country, weaving in the port

117 602

179,28

198 383

302,43

Coastal exporting country, weaving in the city

67 475

102,87

123 192

187,81

Export local, woven in the port

121 067

184,57

199 422

304,02

Local production, embroidery in the city

70 940

108,15

124 232

189,39

Free export zone, integrated into the port

121 067

184,57

199 422

304,02

Free export zone, integrated into the city

70 940

108,15

124 232

189,39

Related costs Gate and Yard

Performance
20 feet
40 feet
XOF
EUR
XOF
EUR

Electricity surcharge

37 422

57,05

41 580

63,39

Weighing axles

2 112

3,22

4 224

6,44

Pont-bascule weighing

9 898

15,09

12 543

19,12

Passage through the scanner

25 064

38,21

25 064

38,21

Redevance customs inspection

25 064

38,21

50 127

76,42

CFS repositioning

25 064

38,21

50 127

76,42

OOG

OOG containers. The published grid indicates a 50% increase %.
Amounts not subject to VAT. The EUR columns are displayed in gray to facilitate reading in XOF.

Franchises and tranches

Parking of containers

The scale of fees transmitted by LCT distinguishes between imports from the local area and the free zone, imports from the hinterland and coastal areas, and then from Niger.
Franchise and tariff tiers depending on the destination
Franchise
Tranche 1
Tranche 2
Maximum tranche
Local imports and free trade zone
4 days
5–9
10–19
20th day and +
Import from hinterland and coastal countries
Franchise 25 days
26th day and +
Niger
Franchise 40 days
41st day and +
Day 0
10
20
30
40
50

Parking amounts per period

Destination
Period
Number of days
20 feet
40 feet
45 feet
Local imports and free trade zone Franchise published: 4 days.
From the 5th to the 9th day inclusive

5

990

1 980

2 079

From the 10th to the 19th day inclusive

10

1 980

3 960

4 158

Starting on the 20th day

—

3 960

7 920

8 316

Import from hinterland and coastal countries
Franchise published: 25 days.

Starting from the 26th day

—

3 960

7 920

8 316

Niger
Franchise published: 40 days.

Starting from the 41st day

—

3 960

7 920

8 316

Effective date and billing unit. Information not specified in the documents submitted. Please confirm these details with LCT before proceeding with the operation.

Equipment

Equipment rental

The amounts below are published in XOF and EUR. The source does not specify the duration or the unit of rental.

Crane and gantry rental

Equipment

XOF

EUR

Mobile crane weighing more than 45 tons

71 999

109,76

Mobile crane of 40 to 45 tons

40 799

62,20

Mobile crane weighing more than 25 to 35 tons

24 500

37,35

Mobile crane weighing more than 15 to 25 tons

16 320

24,88

Mobile crane of 15 tons

12 240

18,66

Mobile crane of 12 tons

12 000

18,29

10-ton mobile crane

10 400

15,85

Mobile crane under 10 tons

9 000

13,72

Mobile MHC crane, maximum 100 tons

983 936

1 500,00

STS portico, maximum 75 tons

1 311 914

2 000,00

Rental of carts and support equipment

Equipment

XOF

EUR

Lift truck weighing more than 15 to 30 tons

24 480

37,32

Lift truck weighing more than 5 to 15 tons

16 320

24,88

2 to 5 ton lift truck

7 200

10,98

Pilotine

100 001

152,45

Docking hook

49 997

76,22

Platform

4 800

7,32

Tractor with 100 horsepower

6 200

9,45

300 horsepower tractor

12 240

18,66

15-ton trailer

4 800

7,32

30-ton trailer

9 600

14,64

50-ton trailer

15 000

22,87

Pousse-wagon

4 800

7,32

Tank

1 000

1,52

Sled

1 000

1,52

Ribbons, nets and pallets

1 000

1,52

Transloading-Containers-Terminal-LCT

Published increments

25 %

Outside of working hours

50 %

Sundays and public holidays

100 %

Nights on Sundays and public holidays

The modalities for the aggregation of these increases are not specified in the sources provided.

Conditions of application

Fees, payment and claims

Setting the prices

LCT determines its rates in compliance with the rules of competition and the concession agreement for the terminal. LCT indicates that it can modify its prices and conditions after prior notification to customers. Discounts or preferential conditions may be granted at its discretion.

Payment and claim

Payment is made in cash or by certified check, unless otherwise agreed. For term deposits, the maturity date is indicated on the invoice. A bill can be contested within eight days of its receipt, with the documents justifying the claim.
8 days
to dispute an invoice

Long-term parking

Goods may be considered abandoned after one month for refrigerated containers and perishable goods, or after three months for other containerized goods, when port and customs fees are not paid within the required time limits.

Refrigerated and perishable: 1 month

Other goods: 3 months

Preparing the operation

Related documents and procedures

onlineBilling

Submit a billing request and the associated documents.

Documentation

Identify the requested documents according to the operation and the type of file.

General procedures

Check the billing, eligibility and access to the terminal steps.

Useful contacts

Find the contact person for a tariff or operational question.

Frequently asked questions

Understanding LCT rates

What do the rates published on this page cover?

The page groups together the land handling for the 20- and 40-foot containers, the associated costs, equipment rental, surcharges, and parking provided by LCT.

The ground handling and equipment rental grid publishes the amounts in CFA francs, code XOF, and in euros.

They are not listed in the current tariff grid published on the LCT official website. The transmitted corpus also contains two different amounts for an inland import handling operation. These amounts are therefore not included on this page.

The published tariff list indicates a 50% surcharge % for OOG containers.

The grid indicates 25 % outside of working hours, 50 % on Sundays and public holidays, and 100 % on Sunday and public holiday nights. The details of the accumulation are not specified.

The scale of duty submitted indicates 4 days for local imports and free zones, 25 days for hinterland imports and coastal countries, and 40 days for Niger.

The documents provided do not specify this. The VAT treatment must be confirmed with LCT before the transaction.

LCT states that it may modify or revise its rates and conditions after prior notification to customers. LCT may also grant discounts or preferential conditions at its discretion.

LCT issues a cash payment or a certified check, unless otherwise agreed. For a term account, the maturity date is indicated on the invoice.

The published deadline is eight days from the receipt of the invoice. The claim must be accompanied by the documents that justify it.

Before submitting your file

Confirm the rate applicable to your transaction

Check the service, the container format, the surcharges, and the billing conditions.